EC6 is the sixth building on CDC's Eastern Creek campus at 17 Roberts Road in western Sydney, under construction alongside EC5 while EC1 to EC4 operate. Per-building capacity has escalated sharply across the campus - 7 MW, then 20, 42 and 54 MW - and the two new buildings were announced on 8 December 2022 as a further 108 MW backed by an extra A$1 billion on top of A$1.5 billion already committed. That takes the campus, CDC's largest Sydney asset, past 200 MW. CDC's second Sydney campus, at Marsden Park, is in early construction and planned for 504 MW and beyond. No separate street address, floor area or building-level capacity is published for EC6 itself.
Facility Specifications
Site information
- Power capacity
- Campus over 200 MW; EC5 and EC6 add 108 MW
Network ecosystem — 3 carriers on-net
Request a Quote
Quote request for: CDC Eastern Creek EC6 view facility
Location
Frequently asked questions
What stage has CDC reached with EC6?
Under construction as of August 2026, alongside EC5. The four operational buildings on the campus are EC1 to EC4.
How much capacity do EC5 and EC6 add at Eastern Creek?
108 MW between them, announced on 8 December 2022 with a further A$1 billion of investment, taking the campus past 200 MW.
How large are the operating Eastern Creek buildings?
7 MW at EC1, 20 MW at EC2, 42 MW at EC3 and 54 MW at EC4 - about 123 MW between them.
Which other operators build at Eastern Creek?
DCI Data Centers, at 90 Peter Brock Drive, and AirTrunk next door at Huntingwood with SYD1 on Huntingwood Drive. All three are distinct companies on distinct sites.