Crusoe Goodnight Campus

10001 Lima Rd, Claude, TX, 79019, US

Get a quote

Metro: Panhandle, TX, US Country: United States Region: North America

Power capacity
933 MW

Crusoe files this one in Texas as Project Llano through the entity GN DC1, LLC; its own name for it is the Goodnight campus, on Lima Road outside Claude in Armstrong County. Seven buildings are planned, four of them at 805,380 sq ft and two at 484,955 sq ft, phased as 530 MW across the first four and 500 MW across the remaining three, for more than a gigawatt in total against a reported project cost of 29 billion dollars. Power is the distinguishing feature. Rather than the flare-gas arrangement Crusoe built its name on, the campus is designed around a purpose-built natural gas plant of up to 933 MW burning pipeline gas, for which an air permit application went to the Texas Commission on Environmental Quality in early 2026 - a plant that would emit more than 4.5 million tons of greenhouse gases a year. Building 3 broke ground on 25 May 2026, Building 4 is targeted for the end of the first quarter of 2027, and first-phase capacity is due between August 2026 and February 2027.

Facility Specifications

Site information

Power capacity
933 MW on-site gas plant applied for; over 1 GW planned

Request a Quote

Quote request for: Crusoe Goodnight Campus view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What is planned at the Goodnight campus?
Seven buildings, four at 805,380 sq ft and two at 484,955 sq ft, phased as 530 MW across the first four and 500 MW across the rest, taking the site past a gigawatt.
How will the campus be powered?
Chiefly from a purpose-built on-site natural gas plant of up to 933 MW running on pipeline gas rather than flare gas, with an air permit application filed with the Texas Commission on Environmental Quality in early 2026.
When does the first capacity arrive?
The first phase is scheduled to go live between August 2026 and February 2027. Building 3 started construction on 25 May 2026 and Building 4 is targeted for the end of the first quarter of 2027.
Which entity is developing the site?
GN DC1, LLC, a Crusoe entity that filed the project in Texas as Project Llano.