Amazon opened the north half of its Indiana Enterprise Center campus on 29 October 2025, and what runs there is unusually specific for a hyperscale site: the buildings were dedicated to training and serving Anthropic's models. Nine of them stand on the IEC-2 lot in Olive Township, between New Carlisle and South Bend, each about 216,000 sq ft and 35 feet tall, with first power taken in January 2025. Indiana Michigan Power, an AEP subsidiary inside PJM, is the supplying utility; AEP is building two 345 kV substations, Larrison Drive and New Prairie, and upgrading its Olive station at a cost near $185m, targeting about 1.1 GW of service by December 2026. The town of New Carlisle supplies water, South Bend takes the sewage and NIPSCO the gas. St. Joseph County Council approved a ten-year abatement of half the real property tax across three parcels totalling 870 acres in August 2024, on an announced $11bn investment and at least 1,000 jobs, with roughly $12.5m a year of property tax projected once the abatements run off.
Facility Specifications
Site information
Colocation space
9 buildings of about 216,000 sq ft each
Request a Quote
Quote request for: Amazon AWS – New Carlisle North DC1 view facility
Location
Interactive map
Frequently asked questions
What runs on the north campus?
Training and inference for Anthropic's models. Amazon opened the nine buildings on 29 October 2025, having taken first power in January 2025.
Which utility supplies the campus?
Indiana Michigan Power, an AEP subsidiary in the PJM market. AEP is building two 345 kV substations, Larrison Drive and New Prairie, alongside upgrades at Olive station, for about $185m and roughly 1.1 GW of service by December 2026.
What tax terms did St. Joseph County agree?
A ten-year abatement of 50% of real property tax over three parcels totalling 870 acres, approved in August 2024, together with an equipment exemption of about 85% for 35 years. Indiana's House Bill 1405 adds a 50-year sales-and-use-tax exemption on equipment, electricity and water running to 2073.
How big will the whole campus become?
Thirty-two buildings and roughly 6.5m sq ft at full build-out, against the sixteen buildings Amazon described when the project was announced in April 2024. The south campus occupies IEC-3 lots across State Road 2.
Where does the site get water and sewer?
Water from the town of New Carlisle, sewer from the City of South Bend and gas from NIPSCO. Amazon holds a permit to discharge 31 million gallons a day of construction-site water.