Amazon AWS – Ridgeland DC4

1626 County Line Rd, Ridgeland, MS, 39157, US

Get a quote

Metro: Jackson, MO, US Country: United States Region: North America

This is the second of Amazon's two Madison County campuses and the larger commitment: $10.5bn on ground taken off Highland Colony Parkway through JDJ Realty in October 2024, about 140 acres in the first tract. Seventeen buildings are planned, the first five targeted for 2028, and the site has been in clearing and dirt work through 2026 under a site plan the Ridgeland aldermen approved unanimously. Entergy Mississippi is building a substation for it. The City of Ridgeland is the sole water supplier and expects to sell 91 to 93 million gallons a year, about 4% of its annual production, underwritten by a $63m water and sewer package.


Request a Quote

Quote request for: Amazon AWS – Ridgeland DC4 view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What stage is the Ridgeland campus at?
Site plan approved and early works under way - tree clearing and dirt work through 2026 - with the first five of seventeen planned buildings targeted for 2028.
How is the water and sewer capacity being paid for?
A $63m package: $30m of water and $7m of sewer work paid directly by Amazon, plus a $26.4m state loan repaid from Amazon property tax. An $8m fire station on Livingston Road comes with it.
What incentives cover the Madison County investment?
SB 2001, passed in January 2024: a $215m state loan for site infrastructure, a $44m appropriation, a permanent sales-and-use tax exemption on equipment and a ten-year corporate income tax exemption, conditioned on $10bn of investment and 1,000 jobs at 125% of the state average wage, with clawbacks.
How much power will the campus draw?
Amazon has published no megawatt figure for Ridgeland. The 616 MW often quoted is carbon-free generation procured from five Mississippi projects, which measures supply rather than site load.