Riot Patforms Rockdale
2721 Charles Martin Hall Rd, Rockdale, TX, 76577, US
Power capacity
700 MW
Riot Platforms mines bitcoin at Rockdale, Texas, on 200 acres in Milam County where seven buildings carry 700 MW of developed capacity. Construction started in 2019 and the first machines ran in 2020. Immersion and air cooling are both in use across the halls. Riot runs the entire site for its own mining load, and its subsidiary E4A manages the substation, which puts the company's power position into the ERCOT market on its own account.
Facility Specifications
Site information
- Power capacity
- 700 MW developed capacity
Power & cooling
- Cooling
- Immersion and air cooling
Request a Quote
Quote request for: Riot Patforms Rockdale view facility
Location
Frequently asked questions
How much power is developed at Rockdale?
700 MW, across seven buildings on 200 acres in Milam County.
What cooling does Riot use at Rockdale?
Both immersion and air cooling, spread across the seven buildings.
When did the Rockdale site start running?
Construction began in 2019 and operations started in 2020.
Who manages the Rockdale substation?
E4A, a Riot subsidiary, which is how Riot takes its own position in the ERCOT market.