Prometheus WY-2

10300 Hat Six Rd, Casper, WY, 82609, US

Get a quote

Metro: Casper, WY, US Country: United States Region: North America

Power capacity
1,500 MW

Carbon capture is the premise of the Casper project rather than an addition to it. Prometheus Hyperscale announced it on 7 October 2025 with Spiritus and Casper Carbon Capture: Spiritus is to supply firm on-site power through its Orchard Power platform, natural gas generation carrying both point-source and direct air capture, while Casper Carbon Capture contributes land, rights of way and access to permitted CO2 sequestration wells in Natrona and Converse Counties. The minimum initial investment is $500 million. Capacity is given two ways by the developer - up to 1.5 GW of IT-ready capacity over multiple phases in the announcement, and 1.25 GW on the projects page, where the site is called the Wyoming Expansion Site. Cooling is planned as proprietary aquifer, non-consumptive water cooling, and first IT-ready power was targeted for 2026. The developer was Wyoming Hyperscale until 4 September 2024; Bernard Looney, formerly chief executive of bp, became its chairman that November and chief executive on 31 March 2026.

Facility Specifications

Site information

Power capacity
Up to 1,500 MW (1.5 GW) IT-ready as announced; 1,250 MW (1.25 GW) on the developer projects page - the two published figures disagree

Power & cooling

Cooling
Aquifer-based non-consumptive water cooling, as planned

Request a Quote

Quote request for: Prometheus WY-2 view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What stage has the Casper project reached?
Announcement. The 7 October 2025 partnership with Spiritus and Casper Carbon Capture is the milestone on record; no construction start or completed phase has been published, against a target of first IT-ready power in 2026.
How will the Casper campus take its power?
Behind the meter, from Spiritus's Orchard Power platform - on-site natural gas generation with point-source capture and direct air capture. No serving utility or substation is named.
Which capacity figure does Prometheus use for Casper?
Both 1.5 GW and 1.25 GW. The October 2025 release says up to 1.5 GW of IT-ready capacity over multiple phases; the current projects page says 1.25 GW.
Where does the captured CO2 go?
Into permitted sequestration wells held by Casper Carbon Capture, a Live Oak Environmental subsidiary, in Natrona and Converse Counties.
How does the Casper site relate to Prometheus's flagship?
The flagship is a separate 506-acre campus near Evanston in Uinta County, with its own conditional use permit and its own capacity path. Casper is the expansion site.