960 MW

AWS bought its way into Pennsylvania nuclear power in March 2024, paying Talen Energy $650 million for the Cumulus data centre campus in Salem Township, Luzerne County, with 960 MW of capacity attached. The buildings take their electricity behind the meter from the Susquehanna Steam Electric Station next door. Berwick is the postal address; the land, 23 holdings in all, lies in Salem Township. AWS pledged $20 billion to Pennsylvania data centres in June 2025, naming Salem Township and Falls Township.

Facility Specifications

Site information

Power capacity
960 MW

Request a Quote

Quote request for: Amazon AWS PHL – 1125 Electron (Bldg 1) view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

How much capacity came with the Berwick campus?
960 MW, as disclosed when Talen Energy announced the sale of the Cumulus campus to AWS for $650 million on 4 March 2024.
How does the Salem Township campus take its power?
Behind the meter from the adjacent Susquehanna Steam Electric Station, under the arrangement AWS took over from Talen Energy.
Which county is the Berwick campus in?
Luzerne County, in Salem Township. Berwick 18603 is the postal address rather than the jurisdiction.
How much has AWS committed to Pennsylvania?
$20 billion pledged in June 2025 for data centres at Salem Township and Falls Township, against more than $26 billion Amazon reports having invested in the state since 2010.