200 MW

Williams County cut the power to this site's construction in June 2023, six weeks after issuing a 45-day order to rectify building code violations, and Atlas Power went on to pay 232,000 dollars in fines before a temporary certificate of occupancy was granted. Residents near the site sued over noise the same year, and settlement agreements went out to them on 13 March 2026. The plant itself has run since 2022 on bitcoin mining and GPU workloads, west of Williston, and it was Mountrail-Williams Electric Cooperative that brought its 200 MW online - a Basin Electric member inside the SPP footprint, where the load was heavy enough that Basin was working on a 600 MW addition to relieve congestion. Full build is projected at 700 MW against a stated project value of 1.9 billion dollars. Governor Doug Burgum announced the project on 26 January 2022. FX Solutions of Montana built it; Atlas Power, of Butte, owns and runs it along with a 75 MW site in its home town.

Facility Specifications

Site information

Power capacity
200 MW energised, 700 MW projected at full build

Request a Quote

Quote request for: Atlas Power Willinston view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What is the Williston site used for?
Bitcoin mining and GPU compute, running since 2022 under Atlas Power's own operation.
Which utility serves the load?
Mountrail-Williams Electric Cooperative, a Basin Electric member in the SPP footprint. It energised 200 MW for the site in 2022.
What regulatory trouble has the site had?
Williams County ordered rectification of building code violations in May 2023 and cut construction power that June. Atlas Power paid 232,000 dollars in fines, and a noise suit brought by neighbours led to settlement agreements issued on 13 March 2026.
How large is the project meant to get?
700 MW at full build, against the 200 MW energised in 2022, with a stated project value of 1.9 billion dollars.