The room at Gaupne is small and long-established: 650 m2 of colocation opened in 2015 at Jostedalsvegen 530 in Luster, Vestland, and the Norwegian company running it is BlueFjords AS, registered in February 2009 at Øyagata 10A in the same village. Power is the pitch. The site sits beside the Leirdøla hydropower station with interconnections to three more, entirely hydroelectric, and Compute Nordic markets 165 MW available from the grid across 60,000 m2 of zoned land next to the existing hall. No internet exchange operates in Sogn, so networks arrive as carrier tails. Compute Nordic Limited, the British company behind the brand, was incorporated in 2019 and renamed in October 2020; the group's larger build is at Mikkeli in Finland, where two 100 MW halls are under contract.
Facility Specifications
Site information
Colocation space
650 m2 in service, with about 60,000 m2 of zoned land alongside
BlueFjords AS, organisation number 993743801, registered in February 2009 and based at Øyagata 10A in Gaupne. Compute Nordic Limited, incorporated in the UK in 2019, carries the brand.
How much space is in service at Jostedalsvegen 530?
650 m2, trading since 2015, with about 60,000 m2 of zoned land alongside it for expansion.
How is the Gaupne site powered?
By hydroelectricity. The building stands next to the Leirdøla hydropower station with interconnections to three more, and the operator states 165 MW available from the grid.
What else does Compute Nordic have under way?
A campus at Mikkeli in Finland through Compute Nordic Finland Oy, registered 12 April 2024, where a February 2026 contract with NYAB covers two 100 MW halls and the high-voltage and substation works around them.