Dataprana La Marque

4995 Farm to Market Rd 1764, La Marque, TX, 77568, US

Get a quote

Metro: La Marque, TX, US Country: United States Region: North America

Power capacity
30 MW

Dataprana broke ground at La Marque, in Galveston County on the Texas Gulf coast, on 23 October 2024, and the plant was running by early June 2025 with a formal launch announced that 22 July. Thirty immersion containers from Intelliflex and Arctic Systems make up a 30 MW site with room for over 5,000 ASIC units; 1,280 Whatsminer M66S machines went in first. The work is digital-asset mining and GPU compute. Dataprana, Inc. directs the site from Aventura, Florida, and puts a further 140 MW across other projects in development.

Facility Specifications

Site information

Power capacity
30 MW

Power & cooling

Cooling
Immersion

Request a Quote

Quote request for: Dataprana La Marque view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What runs at Dataprana's La Marque plant?
Digital-asset mining, GPU compute and Web3 workloads, housed in immersion-cooled containers.
Which county is the La Marque site in?
Galveston County, on the Texas Gulf coast south-east of Houston.
How was the La Marque plant assembled?
From thirty immersion containers supplied by Intelliflex and Arctic Systems, sized for more than 5,000 ASIC units, with 1,280 Whatsminer M66S machines deployed at the start.
When did the Texas site come online?
Early June 2025, about eight months after the 23 October 2024 groundbreaking. Dataprana announced the launch on 22 July 2025.