Thirty-seven hectares at Im Technologiepark 1 in 15236 Frankfurt (Oder) are being assembled for a 350 MW AI and cloud campus, with 300 MW of battery storage and on-campus solar in the design. The City of Frankfurt (Oder) confirmed planning maturity under section 33 of the federal building code in June 2026, and the local building authority gave a positive preliminary view that a permit is achievable under Brandenburg's building rules once an application is filed. No permit has been issued and no ground broken. The developer is Frankfurt DATA FFO AI GmbH, a project vehicle of the SolWo Group that took its present name in February 2026 and is a member of the German Datacenter Association. The site is in the Brandenburg border city on the Oder, roughly 90 km east of Berlin, rather than in Frankfurt am Main.
Facility Specifications
Site information
Power capacity
350 MW planned; 300 MW of on-site battery storage
Request a Quote
Quote request for: Frankfurt Oder – Building 5 view facility
Location
Interactive map
Frequently asked questions
What planning stage has the Frankfurt (Oder) campus reached?
Planning maturity under section 33 of the German federal building code, confirmed by the city in June 2026, plus a positive preliminary assessment from the building authority. A building permit application still has to be filed.
How much power is planned for the Oder campus?
350 MW, with 300 MW of battery energy storage and solar generation on the campus itself. The developer does not state whether the 350 MW is IT load or grid connection.
Which company is behind the Frankfurt (Oder) project?
Frankfurt DATA FFO AI GmbH, a project vehicle of the SolWo Group registered in Frankfurt (Oder), which adopted its current name in February 2026.
How much land does the Frankfurt (Oder) scheme cover?
37 hectares. No building floor area has been published.