Microsoft has asked Varde Kommune for the planning instruments it needs to build on roughly 79 hectares at Kastkaervej, between the villages of Lunde and Norre Nebel in west Jutland. The applications went in on 11 December 2025 and propose three two-storey data halls, cut back from four, rising to 23 metres with up to 9 metres of rooftop plant above that. The council voted on 24 June 2026 to open the local-plan process only conditionally: Microsoft must set out by 30 September 2026 how it will engage the surrounding community, and must offer neighbours within 500 metres a buyout, cash compensation or a value guarantee. On the council's own timetable, building would begin in 2027 or 2028 and the site would run from around 2030. A second and larger Microsoft scheme is in front of the same kommune at Tinghoj on Ringkobingvej, some 150 hectares and five halls.


Request a Quote

Quote request for: Microsoft Lunde – Building 3 view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What stage is the Lunde project at?
Pre-permission. Microsoft lodged local-plan and municipal-plan applications with Varde Kommune on 11 December 2025, and the council agreed in June 2026 to begin the process only on conditions.
What conditions did Varde Kommune attach?
Microsoft must account by 30 September 2026 for how it will engage the local area, and must offer neighbours within 500 metres a property buyout, financial compensation or a value guarantee.
How many halls are proposed at Kastkaervej?
Three, reduced from four. Each is two storeys to 23 metres, with rooftop technical plant permitted up to a further 9 metres, for a 32-metre maximum.
When could the Lunde site be operating?
Varde Kommune's timetable points to construction in 2027 or 2028 and operation around 2030.
Who should I contact about capacity near Norre Nebel?
Send us an inquiry. Microsoft's Lunde scheme is unbuilt, while GlobalConnect already runs a facility at Industrivej 16 in Norre Nebel - a different operator at the same postcode.