Malta's government ICT systems run from a purpose-built hall on Old Railway Track in Santa Venera, opened on 7 December 2011 at a cost of EUR 7 million and operated by the Malta Information Technology Agency on its own hardware. It carries eGovernment, eHealth, eID and eLearning platforms for more than 28,000 users, about a million emails a day and 450 TB of storage. The build laid 7,000 m of copper and 8,000 m of fibre cabling. The agency has issued no square-metre or megawatt figure for it in the years since.
Request a Quote
Quote request for: MITA Data Centre view facility
Location
Frequently asked questions
Which systems does the Santa Venera data centre carry?
Maltese government platforms - eGovernment, eHealth, eID cards, eLearning for more than 45,000 teachers and students, email and billing - hosted on hardware MITA owns and manages itself.
When was the MITA data centre built?
It was launched on 7 December 2011 at a cost of EUR 7 million, replacing a centre that could no longer meet the requirements of government ICT.
What does the Tier III wording attached to MITA describe?
A site specification based on the TIA-942 standard, stated at launch alongside ISO 27001 and the EU Code of Conduct on Data Centres. That is a different scheme from an Uptime Institute Tier award, and no Uptime award exists for the agency.
How big is the Santa Venera facility?
MITA publishes no floor area or megawatt figure. What it disclosed at launch was the cabling - 7,000 m of copper and 8,000 m of fibre - and the service scale: 450 TB of storage and 16,000 accounts.