Power capacity
480 MW

T5 announced the Grayslake campus on 2 May 2024: 160 acres in Lake County, Illinois, already zoned for data centre use before the purchase, with up to 480 MW at full build and a first 60 MW targeted for the fourth quarter of 2027. An electrical substation is planned on the site itself to carry efficient and redundant utility power. The land is banked and the campus has no operating capacity. Grayslake is one of several Chicago-market sites T5 holds; the company added CHI V in Elk Grove Village on 26 March 2025, a 220,000 sq ft building of 36 MW due for occupancy in 2028. The T5 platform, formed in 2019, is owned by QuadReal Property Group and T5's principals.

Facility Specifications

Site information

Power capacity
Up to 480 MW at full build; first 60 MW targeted Q4 2027

Request a Quote

Quote request for: T5 Data Centers – T5@Grayslake Campus view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What is planned at T5's Grayslake campus?
Up to 480 MW across 160 acres, with a first phase of 60 MW targeted for the fourth quarter of 2027 and an on-site substation planned.
What stage is the Grayslake site at?
Land-banked. T5 announced it on 2 May 2024, the ground was already zoned for data centre use, and no building has been constructed.
Who owns the T5 platform?
QuadReal Property Group, the real-estate arm of British Columbia Investment, together with T5's principals. QuadReal added an $8 billion equity commitment in February 2025.
How does Grayslake fit alongside T5's other Chicago sites?
It is the land-banked one. T5 also runs T5@Chicago at 200 Innovation Drive in Elk Grove Village and bought CHI V there, a 220,000 sq ft, 36 MW building, on 26 March 2025.