EdgeCore Florence Tech Park – Building 1

E Arizona Farms Rd & N Attaway Rd, Florence, AZ, 85143, US

Get a quote

Metro: Eloy, AZ, US Country: United States Region: North America

Colocation space
332,100
sq ft
Power capacity
72 MW

Florence Tech Park is Ryan Companies US, Inc.'s scheme in Pinal County, and EdgeCore's Florence proposal sits beside it on a separate portion of the 1,810-acre Dobson Farms master plan, approved in 2009 and largely undeveloped since. EdgeCore's part, presented to the Florence Planning and Zoning Commission on 4 September 2025, is up to ten two-storey buildings of 332,100 sq ft each at 72 MW apiece - roughly 720 MW - with four substations. Dobson Land Investment and Strand 600 brought their own proposals to the same hearings, some 780 acres between the three applicants, and the town has since approved data centre use across 1,619 acres. The ground is farmland; construction has not begun and no availability date has been given.

Facility Specifications

Site information

Colocation space
Up to ten buildings of 332,100 sq ft each, as proposed
Power capacity
72 MW per building, about 720 MW proposed

Request a Quote

Quote request for: EdgeCore Florence Tech Park – Building 1 view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What has EdgeCore proposed at Florence?
Up to ten two-storey buildings of 332,100 sq ft, 72 MW each and roughly 720 MW in total, with four substations, on part of the Dobson Farms master plan.
Whose scheme is Florence Tech Park?
Ryan Companies US, Inc.'s. EdgeCore holds a separate portion of the same Dobson Farms ground, and Dobson Land Investment and Strand 600 brought further proposals to the same hearings.
What stage is the Florence project at?
Rezoning. The proposals went to the Florence Planning and Zoning Commission on 4 September 2025 and need a Major General Plan Amendment and PUD amendments; the town has since approved data centre use across 1,619 acres.
When will capacity be available at Florence?
The ground is farmland and construction has not started; the applicants have published no availability date and the entitlements are still being amended.