Cherwell District Council approved reserved matters for a data centre on the D1 site at Graven Hill, off Circular Road at Ambrosden on the south-eastern edge of Bicester, on 6 August 2026. Application 25/03310/REM was submitted in December 2025 under outline permission 22/01829/OUT and decided by delegated officers, and the consent runs under storage and distribution use class B8. Graven Hill Purchaser Ltd, a property development and letting company, is the applicant; no operator has been named for the completed buildings. An energy statement by SLR Consulting puts total demand at 3,810,000 MWh a year, which the document compares to roughly a million Oxfordshire homes, while the application gives no megawatt rating at all. Cooling is closed-loop and water-light, free for around 60% of the year with mechanical coolers behind it. The developer has told the Graven Hill residents' association that a power supply contract is already secured, without disclosing terms, and puts employment at 500 to 800 jobs once operational, about half of them remote. BREEAM Excellent is an aspiration written into an outline condition rather than a rating held.

Facility Specifications

Power & cooling

Cooling
Closed-loop, free cooling ~60% of year plus mechanical coolers

Request a Quote

Quote request for: Graven Hill Campus – Building 3 view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What stage has the Graven Hill scheme reached?
Consented and unbuilt. Cherwell District Council permitted reserved matters 25/03310/REM on 6 August 2026, under the outline permission granted as 22/01829/OUT.
Which company is behind the Bicester data centre?
Graven Hill Purchaser Ltd, a property development and letting company, is the applicant and developer. It has named no operator for the finished buildings.
How much energy is the scheme expected to use?
3,810,000 MWh a year on the application's own energy statement, almost all of it unregulated process load, with 4,265 MWh regulated. The papers carry no megawatt rating.
How will the Graven Hill buildings be cooled?
On a closed loop, with free cooling available for roughly 60% of the year and mechanical coolers covering the remainder, and minimal water draw.
Which part of Graven Hill takes the data centre?
The D1 site on the south-eastern flank of the hill, off Circular Road at Ambrosden, next to St David's Barracks and inside Bicester parish.