Microsoft runs a public construction blog for this project, which is unusual enough in Northern Virginia to be the reason to read the record: it dates the start to May 2024, gives an eighteen to twenty-four month programme, and reported steel going up on the North End in January 2025 while rock drilling continued on the South End into March. Prince William County holds the ground as GPIN 7496-88-1217, 83.00 acres at 10350 Hansen Farm Road under a Bristow ZIP, owned by Microsoft Corporation and annotated Gainesville Tech Park, while Microsoft addresses the site to Manassas. Clark Technologies, a division of Clark Construction, is the general contractor, and the county permits noisy work from 7am to 10pm on weekdays. Capacity, utility and water arrangements are unpublished.
Request a Quote
Quote request for: Microsoft Hansen Farm view facility
Location
Interactive map
Frequently asked questions
What stage is the Hansen Farm build at?
Under construction since May 2024 on an eighteen to twenty-four month programme. Steel erection had started on the North End by January 2025, with site work continuing on the South End into March and building enclosure targeted for the summer.
Who is building it?
Clark Technologies, a division of Clark Construction, as general contractor.
How is the parcel recorded?
Prince William County lists GPIN 7496-88-1217 at 10350 Hansen Farm Road, 83.00 acres, owned by Microsoft Corporation and annotated Gainesville Tech Park, with two buildings on the tract.
Which town is the site in?
Microsoft addresses it to Manassas. The county parcel record and the 20136 ZIP place it in Bristow, and the county annotates the tract Gainesville Tech Park - three names for one 83-acre holding.