One of two near-identical shells COPT Defense Properties built in 2019 on a 19.5-acre parcel off Maries Road, MP-2 runs to 212,960 sq ft over two storeys with 28-foot walls, and Loudoun County assesses its replacement cost at $130.3 million. The county names the improvement COPT-AMAZON, which is unusual: COPT never identifies tenants building by building, and the assessor does. Title sits with Maries Tech Park LLC, care of COPT's Columbia headquarters, on Lot 5 of the Tall Oaks subdivision. The pair exists because of a 2018 site plan amendment, SPAM-2018-0029, which converted three approved flex-industrial buildings into two data centres on land zoned PDIP. The assessor rates the structure 98 per cent good, depreciating the figure to $127.7 million. COPT builds powered shells for hyperscale and US Government customers on build-to-suit terms and sells no colocation anywhere, so the electrical and mechanical plant here belongs to the tenant and is not disclosed. Across the company it owns and operates more than thirty such buildings, about 6.3 million sq ft, and it keeps more than 150 personnel holding TS/SCI clearances to meet its customers' security requirements.

Facility Specifications

Site information

Colocation space
212,960 sq ft, two storeys, 28 ft wall height

Request a Quote

Quote request for: COPT MP-2 view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

Who is the tenant?
Loudoun County's assessment record names the improvement COPT-AMAZON. COPT does not confirm tenants building by building.
What did the 2018 entitlement approve?
Loudoun application SPAM-2018-0029 amended an approved site plan to convert three flex-industrial buildings into two data centres, on PINs 030376823000 and 030382006000, zoned PDIP.
What does COPT deliver in a building like this?
Land, entitlements, shell construction and utility power, on build-to-suit terms and within 12 to 15 months of land acquisition. UPS, generators, cooling and IT fit-out are the tenant's scope and are not disclosed by either party.
How large is the building?
212,960 sq ft gross across two storeys, 28-foot wall height, fully sprinklered, completed in 2019 and assessed as 100 per cent complete.