ACS Fort Worth Campus

10059-10197 Hicks Field Rd, Fort Worth, TX, 76179, US

Get a quote

Metro: Dallas, TX, US Country: United States Region: North America

Colocation space
251,303
sq ft
Power capacity
140 MW

Five buildings are planned on 107 acres at Hicks Field Road in north Fort Worth, and the first three are registered and under way: DFW 11 at 10200 Hicks Field Road, 251,303 sq ft over two storeys with two data halls of 25,075 sq ft each and a $280 million build cost, then DFW 12 and DFW 13 at 283,274 sq ft apiece, each holding four halls of 29,427 sq ft. An anchor lease signed on 15 July 2026 commits about 140 MW of critical IT load across the three to a single undisclosed hyperscaler, with rights to roughly 100 MW more in the two buildings still to come. Coravel operates the campus - the brand launched the same day for the 50-50 joint venture between ACS Group and Global Infrastructure Partners - with Turner Construction building it and Corgan as architect. Oncor plans a substation next to the site inside ERCOT, and cooling is designed as a closed water loop. Completion runs from 26 June 2027 for DFW 11 to 17 May 2028 for DFW 12.

Facility Specifications

Site information

Colocation space
DFW 11 251,303 sq ft; DFW 12 and DFW 13 283,274 sq ft each
Power capacity
About 140 MW critical IT committed; rights to about 100 MW more

Power & cooling

Cooling
Closed water loop, as filed

Request a Quote

Quote request for: ACS Fort Worth Campus view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

Which company will operate the Hicks Field Road campus?
Coravel, the brand launched on 15 July 2026 for the 50-50 joint venture between ACS Group and Global Infrastructure Partners, under chief executive Howard Boville. Turner Construction, an ACS subsidiary, is the contractor.
How much capacity is already committed at Fort Worth?
About 140 MW of critical IT load across DFW 11, DFW 12 and DFW 13, leased to one undisclosed hyperscaler, with rights to a further 100 MW across two later buildings.
When do the Fort Worth buildings complete?
DFW 11 on 26 June 2027, DFW 13 on 3 January 2028 and DFW 12 on 17 May 2028, on the dates carried by the Texas construction registrations.
Which utility serves the Fort Worth data centre campus?
Oncor, inside ERCOT, with a substation planned adjacent to the 107-acre site. The campus is designed around a closed water loop to hold down site water use.