Microsoft broke ground at Palmetto, in south Fulton County, in April 2024, aiming for completion at the start of October 2025. Filings with the Georgia Department of Community Affairs put the site at up to 116 acres carrying a 250,000 sq ft data centre; Microsoft bought the original ground in 2020 and added about 20 acres for $6 million in early 2024. Palmetto was announced with East Point and Douglasville as the three metro Atlanta sites of the East US 3 Azure region. Microsoft moved in August 2026 to void Fulton County's ten-year tax break, granted in 2020.
Facility Specifications
Site information
- Colocation space
- 250,000 sq ft
Request a Quote
Quote request for: Microsoft Palmetto view facility
Location
Frequently asked questions
When did construction start at Palmetto?
April 2024, with completion targeted for the start of October 2025.
How large is the Palmetto site?
Up to 116 acres under filings with the Georgia Department of Community Affairs, carrying a 250,000 sq ft building.
Which Azure region does Palmetto serve?
East US 3, announced together with sister projects at East Point and Douglasville.
What is the position on the Palmetto tax break?
Fulton County granted a ten-year property tax break in 2020, and Microsoft moved to void the agreement in August 2026.