Switch LAS VEGAS 14

5680 Badura Ave, Las Vegas, NV, 89118, US

Get a quote

Metro: North Las Vegas, NV, US Country: United States Region: North America

Site preparation on the 14-to-18 block of Switch's Core Campus was under way in the second quarter of 2022, when $60.9 million of campus capital expenditure covered construction and tenant improvements at Las Vegas 15 plus site work for buildings 14, 16, 17 and 18. That is the last building-level detail Switch published: DigitalBridge and IFM Investors took the company private in December 2022, and its facility list stops at the end of 2021 with nine operating Core Campus buildings — up to 2,340,000 gross sq ft and 311 MW — running to Las Vegas 12. Clark County approved a further building, LAS 19, on 17 June 2026.


Request a Quote

Quote request for: Switch LAS VEGAS 14 view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What stage did Switch record for this building?
Site preparation. Its August 2022 quarterly release named Las Vegas 14 among four Core Campus future facilities then in site work, alongside 16, 17 and 18, while Las Vegas 15 was under construction with tenant improvements.
Which buildings make up Switch's Las Vegas estate?
Nine were operating at the end of 2021 — Las Vegas 2, 4, 5, 7, 8, 9, 10, 11 and 12 — with five future facilities behind them adding 1,600,000 gross sq ft and 180 MW. The numbering has never used 1, 3, 6 or 13, so 14 follows 12. Clark County approved LAS 19, about 56,000 sq ft on nine acres east of Edmond Street, on 17 June 2026.
Why has nothing been published at building level since 2022?
Switch was taken private by DigitalBridge and IFM Investors in December 2022 and stopped filing with the SEC. Its website describes the Core Campus rather than individual Las Vegas buildings.
How much capacity does the Core Campus carry?
Up to 311 MW across nine operating buildings and up to 2,340,000 gross sq ft at the end of 2021. Switch markets the completed campus at up to 495 MW, fed from the Audet substation it built with NV Energy.