CloudHQ LC10
22210 Loudoun County Parkway, Ashburn, VA, 20147, US
Colocation space
789,676
m²
Power capacity
1,256 MW
Fourteen data centres are planned on the CloudHQ campus directly off Loudoun County Parkway in Ashburn, and LC3 and LC4 are the two now under construction. The master plan covers close to 8.5 million sq ft - 789,676 m2 - and CloudHQ publishes 1,256 MW of total critical IT load for it, 756 MW of that shown as available, with more than 1.7 GW of customer load across the full fourteen buildings. A single customer can take a run of buildings as a campus within the campus, which is how CloudHQ sells in Loudoun County: whole shells to one occupier rather than halls to several. Ready-for-service on the buildings now moving is marketed at twenty months.
Facility Specifications
Site information
- Colocation space
- c. 8.5 million sq ft (789,676 m2) planned across fourteen buildings
- Power capacity
- 1,256 MW total critical IT load, 756 MW shown as available
Request a Quote
Quote request for: CloudHQ LC10 view facility
Location
Frequently asked questions
How many buildings will CloudHQ build on its Ashburn campus?
Fourteen. LC3 and LC4 are the two under construction; the remainder follow customer demand.
What capacity does CloudHQ publish for the Loudoun County Parkway campus?
1,256 MW of total critical IT load with 756 MW shown as available, and more than 1.7 GW of customer critical IT load once all fourteen buildings are up.
What does a campus within a campus mean at Ashburn?
One customer takes a group of buildings on the site for its own use, with its own perimeter, instead of taking space inside a shared building.
How quickly can the Ashburn campus deliver new capacity?
CloudHQ markets ready-for-service within twenty months on the buildings now in construction.