SDC Quincy Campus
2200 M St NE, Quincy, WA, 98848, US
SDC Quincy is Sabey's five-building campus at 2200 M Street NE in Quincy, launched in 2011 on Grant County hydro power priced at 3.8 cents per kWh through an on-site substation. Sabey's own figures put campus critical capacity at 123 MW in one statement and 130 MW in another, with 50 to 60 MW of utility power delivered today, and built space at 525,000 to 530,000 sq ft across the five buildings, of which 438,000 sq ft is mission-critical floor. The latest phase, two buildings adding 85 MW, was completed in June 2023 after a February 2022 announcement that named an anchor service-provider tenant. Backup is N+1 with 2 MW generators and 72 hours of fuel, evaporative and economizer cooling holds annualized PUE between 1.2 and 1.25, Building B runs chilled water through CRAHs and Building E is enabled for liquid cooling. Fifteen carriers including Azure ExpressRoute, Comcast, Lumen, Megaport and Zayo meet in the on-site meet-me rooms.
Facility Specifications
Power & cooling
- Redundancy
- N+1 electrical, 2 MW generators, 72-hour fuel
- Cooling
- evaporative and economizer, hot/cold aisle containment, PUE 1.2 to 1.25
Compliance
Platforms & amenities
- Platforms & services
- Megaport SDN, Azure on-ramp
- Amenities
- on-site substation, 24/7 security, mantraps, biometric locks, loading docks, conference rooms, showers, office and storage space
Network ecosystem — 4 carriers on-net
Notable: Microsoft (AS8075)
Cloud on-ramps
4 networks, 1 IX, Azure ExpressRoute, Megaport, Comcast, Lumen, Zayo, Astound, Ziply, LS Networks, on-site meet-me rooms