Microsoft Goodyear (PHX70)

3785 N Citrus Rd, Goodyear, AZ, 85395, US

Get a quote

Metro: Phoenix, AZ, US Country: United States Region: North America

What constrained this campus was sewer capacity, not electricity. The plans Microsoft lodged with the City of Goodyear had each of five buildings drawing a million gallons of water a day, roughly 1.83 billion gallons a year, and the city did not have the wastewater plant to carry it. The two sides rewrote their development agreement in March 2023: the campus moved to air cooling, took a wastewater allowance capped at 1.2 million gallons a day, had its impact fees reimbursed and replaced, and committed to finishing a dedicated discharge line by 31 August 2024. By December 2024 the site was being described as zero-water cooled. The land came in three purchases - 279 acres near Phoenix Goodyear Airport in August 2018 for about 48 million dollars, 147 acres more in April 2019 for about 37 million, and 100 acres from First Industrial Realty Trust in June 2026 for 131 million. The West US 3 region the campus anchors launched on 15 June 2021. Microsoft runs a second Arizona campus at El Mirage, which coverage of Goodyear regularly folds into this one.

Facility Specifications

Power & cooling

Cooling
Air cooled since the March 2023 development agreement

Request a Quote

Quote request for: Microsoft Goodyear (PHX70) view facility
We'll route your request to the facility and email you a copy.

Location

Interactive map

Frequently asked questions

What did the 2023 development agreement change?
The campus moved from evaporative to air cooling, accepted a wastewater cap of 1.2 million gallons a day, and committed to completing a dedicated discharge line by 31 August 2024.
How much water was originally planned?
One million gallons a day for each of five buildings, around 1.83 billion gallons a year, in the plans lodged with the city. An earlier analysis given to the council estimated about 56 million gallons of potable water a year.
How much land does the campus hold?
279 acres bought in August 2018, 147 acres in April 2019 and 100 acres in June 2026, the last for 131 million dollars from First Industrial Realty Trust.
Which other Arizona campus does Microsoft operate?
El Mirage, a separate site that coverage of the Phoenix market frequently conflates with Goodyear.